- Status
- In Force
- Penalty ceiling
- Regulated
Does it bind you?
Business-side roles with duties under this instrument.
Any Person14
Data Controller1
Plus 1 duty on the regulator, Crown ministers and public bodies — folded into the section list below.
Other Acts binding the same actors
If a role above is yours, these are the other instruments that most often bind it.
Any Person — also bound by 2340 other Acts
Human Medicines Regulations 2012
184 duties
Merchant Shipping Act 1995
144 duties
Insolvency (England and Wales) Rules 2016
104 duties
Communications Act 2003
92 duties
Road Traffic Act 1988
92 duties
Data Controller — also bound by 35 other Acts
UK GDPR (retained EU law)
127 duties
Data Protection Act 2018
46 duties
What it requires
Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.
s.art004
Application to existing HVDC systems and DC-connected power park modules
Regulated
- Notify system operator before upgrading HVDC equipmentAny Person
s.art039
Frequency stability requirements
Regulated
- Your DC-connected power park must meet fast frequency response signal processing requirementsAny Person
s.art040
Reactive power and voltage requirements
Regulated
- Ensure your DC-connected power park module meets voltage and reactive power requirementsAny Person
s.art041
Control requirements
Regulated
- Limit voltage changes when synchronising DC-connected power park modules to the AC networkAny Person
s.art047
Frequency stability requirements
Regulated
- Agree technical communication modalities for frequency response with remote-end station ownerAny Person
s.art060
General provisions
Regulated
- Complete operational notification for new DC-connected power park modulesAny Person
s.art062
ION for DC-connected power park modules
Regulated
- Provide technical data and studies to obtain interim operational notificationAny Person
s.art063
FON for DC-connected power park modules
Regulated
- Provide compliance statement and technical data updates when requested by the system operatorAny Person
s.art064
Limited operational notification for DC-connected power park modules
Regulated
- Inform system operator of capability loss or non-compliance and apply for LONAny Person
s.art066
Principles of cost-benefit analysis
Regulated
- Assist in cost-benefit analyses and follow prescribed methodology when performing your ownAny Person
s.art067
Common provisions for compliance testing
Regulated
- Test your HVDC system or power park to prove complianceData Controller
s.art068
Common provisions on compliance simulation
Regulated
- Provide simulation report and validated model for HVDC system or DC-connected power park moduleAny Person
s.art069
Responsibility of the HVDC system owner and DC-connected power park module owner
Regulated
- Ensure ongoing compliance and notify the system operator of changes, incidents, and testsAny Person
s.art070
Tasks of the relevant system operator
Regulated
Other duties (1) — Crown / regulator
- System operator must assess HVDC compliance and publish requirementsStatutory regulator
s.art074
Compliance simulations for DC-connected power park modules and remote-end HVDC converter units
Regulated
- Run compliance simulations for grid connection of HVDC systems and power park modulesAny Person
s.art079
Request for derogations by an HVDC system owner or DC-connected power park module owner
Regulated
- Submit a derogation request to your system operator with all required detailsAny Person
85 other provisions — procedural and definitional
s.annex iii para.1
Synchronous Area Voltage Range Time period for operation . ....
s.annex iii para.2
Synchronous Area Voltage Range Time period for operation . ....
s.annex i para.1
Table 1: Minimum time periods an HVDC system shall be...
s.annex iv para.1
Figure 5: The diagram represents boundaries of a U-Q/Pmax-profile with...
s.annex iv para.2
Table 6: Parameters for the Inner Envelope in the Figure....
s.annex viii para.1
Voltage range Time period for operation 0.85 pu-0.90 pu 60...
s.annex viii para.2
Voltage range Time period for operation 0.85 pu-0.90 pu 60...
s.annex viii para.3
Maximum range of Q/Pmax Maximum range of steady-state voltage level...
s.annex vii para.1
Voltage Range Time period for operation 0.85 pu-0.90 pu 60...
s.annex vii para.2
Voltage Range Time period for operation 0.85 pu-0.90 pu 60...
s.annex vii para.3
Figure 7: U-Q/Pmax-profile of a DC-connected power park module at...
s.annex vii para.4
Range of width of Q/Pmax profile Range of steady-state Voltage...
s.annex vi para.1
Frequency range Time period for operation 47.0 Hz-47.5 Hz 20...
s.annex v para.1
Figure 6: Fault-ride-through profile of an HVDC converter station. The...
s.annex v para.2
Voltage parameters [pu] Time parameters [seconds] Uret 0.00-0.30 tclear 0.14-0.25...
s.art001
Subject matter
s.art002
Definitions
s.art003
Scope of application
s.art005
Regulatory aspects
s.art006
Multiple TSOs
s.art007
Recovery of costs
s.art008
Public consultation
s.art009
Stakeholder involvement
s.art010
Confidentiality obligations
s.art011
Frequency ranges
s.art012
Rate-of-change-of-frequency withstand capability
s.art013
Active power controllability, control range and ramping rate
s.art014
Synthetic inertia
s.art015
Requirements relating to frequency sensitive mode, limited frequency sensitive mode overfrequency and limited frequency sensitive mode underfrequency
s.art016
Frequency control
s.art017
Maximum loss of active power
s.art018
Voltage ranges
s.art019
Short circuit contribution during faults
s.art020
Reactive power capability
s.art021
Reactive power exchanged with the network
s.art022
Reactive power control mode
s.art023
Priority to active or reactive power contribution
s.art024
Power quality
s.art025
Fault ride through capability
s.art026
Post fault active power recovery
s.art027
Fast recovery from DC faults
s.art028
Energisation and synchronisation of HVDC converter stations
s.art029
Interaction between HVDC systems or other plants and equipment
s.art030
Power oscillation damping capability
s.art031
Subsynchronous torsional interaction damping capability
s.art032
Network characteristics
s.art033
HVDC system robustness
s.art034
Electrical protection schemes and settings
s.art035
Priority ranking of protection and control
s.art036
Changes to protection and control schemes and settings
s.art037
Black start
s.art038
Scope
s.art042
Network characteristics
s.art043
Protection requirements
s.art044
Power quality
s.art045
General system management requirements applicable to DC-connected power park modules
s.art046
Scope
s.art048
Reactive power and voltage requirements
s.art049
Network characteristics
s.art050
Power quality
s.art051
Operation of HVDC systems
s.art052
Parameters and settings
s.art053
Fault recording and monitoring
s.art054
Simulation models
s.art055
General provisions
s.art056
EON for HVDC systems
s.art057
ION for HVDC systems
s.art058
FON for HVDC systems
s.art059
Limited operational notification for HVDC systems/derogations
s.art061
EON for DC-connected power park modules
s.art065
Identification of costs and benefits of application of requirements to existing HVDC systems or DC-connected power park modules
s.art071
Compliance testing for HVDC systems
s.art072
Compliance testing for DC-connected power park modules and remote-end HVDC converter units
s.art073
Compliance simulations for HVDC systems
s.art075
Non-binding guidance on implementation
s.art076
Monitoring
s.art077
Power to grant derogations
s.art078
General provisions
s.art080
Request for a derogation by a relevant system operator or relevant TSO
s.art081
Request for derogations from the provisions of Title III by a DC-connected power park module owner
s.art082
Register of derogations from the requirements of this Regulation
s.art083
Monitoring of derogations
s.art084
Amendment of contracts and general terms and conditions
s.art085
HVDC System or DC-connected power park modules connecting with synchronous areas or control areas not bound by EU legislation
s.art086
Entry into force
Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.