High-rise fire safety compliance checklist
Quick compliance checklist for high-rise residential building duty holders. Verify your building meets Fire Safety (England) Regulations 2022 requirements for buildings 18 metres or higher, or 7+ storeys.
High-rise fire safety compliance at a glance
Use this checklist to verify your high-rise residential building (18 metres or higher, or 7+ storeys) meets Fire Safety (England) Regulations 2022 requirements. This is for experienced duty holders who know their obligations.
Applies to: Buildings in England with at least 2 residential units that are either 18 metres or higher, or have 7 or more storeys.
-
Secure information box installed and populated
Verify:
- Box installed near main entrance or firefighter access point
- Uses Gerda key lock (or your local FRS standard)
- Contains hard copy floor plans for every floor
- Contains building orientation plan
- Contains your name and 24/7 UK contact details
- Information is current and dated
-
Floor plans prepared and submitted to FRS
Verify:
- Floor plans exist for every floor
- Plans show layout, fire safety equipment, escape routes, and firefighting equipment
- Building orientation plan prepared (single page showing overall layout)
- Electronic copies submitted to local Fire and Rescue Authority
- Plans updated after any building changes
-
Wayfinding signage installed on all floors
Verify:
- Floor number visible on every floor (lift lobbies and stairwells)
- Each stairwell has unique identifier (e.g., Stairwell A, Stairwell B)
- Signs are photoluminescent (glow in dark)
- Signs positioned at eye level (1.4-1.7m)
- Signs not faded, damaged, or obscured
- Stairwell identifiers match floor plan labels
-
Quarterly fire door inspections up to date
Verify:
- Last quarterly inspection of communal doors within past 3 months
- Last annual inspection of flat entrance doors within past 12 months
- Inspection records complete (date, inspector, findings, remedial actions)
- Any defects identified have been remediated
- Self-closers working on all fire doors
- Intumescent strips and smoke seals intact
Fire door inspection requirements
Detailed guidance on what to check, inspection frequencies, and competency requirements
-
Monthly lifts and equipment checks documented
Verify (where installed):
- Firefighting lift checked this month (firefighting mode, communication, recall)
- Evacuation lift checked this month (operation, communication, power)
- Automatic door release mechanisms checked (doors release and close on alarm)
- Evacuation alert system checked (audible throughout building)
- Records kept with date, inspector name, findings, and actions
-
External wall information recorded and submitted
Verify:
- External wall materials documented (cladding, insulation, fixings)
- Wall system design recorded (construction methodology, layers)
- Fire safety features documented (cavity barriers, fire stopping)
- Information provided to Fire and Rescue Authority
- Records updated after any external wall alterations
- Ready to provide to residents on request (buildings 18m+)
-
Resident fire safety information distributed
Verify:
- All residents have received fire safety information
- Information explains the evacuation strategy (stay put or simultaneous)
- Information explains what to do if fire discovered or alarm sounds
- Information explains fire door importance and why they must stay closed
- Your contact details included for reporting concerns
- Information in accessible formats for all residents
- New residents receive information on move-in
-
Fire risk assessment covers external walls
Verify:
- Fire risk assessment is written and dated
- Assessment explicitly covers external walls (including cladding, balconies)
- Assessment covers flat entrance doors opening onto common parts
- Assessment reviewed regularly, and after any significant change
- Significant findings recorded and actioned
- Assessor was competent (consider BAFE SP205 certification for complex buildings)
High-rise fire safety requirements
Full guide to all Fire Safety (England) Regulations 2022 requirements for high-rise residential buildings
Key inspection frequencies
Item Frequency Applies to Communal fire doors Quarterly Buildings over 11m Flat entrance doors Annual Buildings over 11m Firefighting lifts Monthly Buildings 18m+ or 7+ storeys Evacuation lifts Monthly Buildings 18m+ or 7+ storeys Automatic door release Monthly Buildings 18m+ or 7+ storeys Fire risk assessment review Regularly, and after any significant change All buildings Records to maintain
Fire and Rescue Authority inspectors will ask to see:
- Fire risk assessment (written, dated, signed)
- Fire door inspection records (quarterly communal, annual flat doors)
- Monthly lift and equipment check records
- External wall information records
- Proof of resident information distribution
- Evidence of floor plans submitted to FRA
- Any remedial work completion records
Detailed guidance
Fire safety for high-rise buildings
Comprehensive guide to all Fire Safety (England) Regulations 2022 duties for high-rise residential buildings
Fire door inspections
Detailed guidance on fire door inspection requirements, what to check, and competency
legislation.gov.uk
Fire Safety (England) Regulations 2022 (opens in a new tab)
Full text of the regulations
gov.uk
Government guidance on Fire Safety Regulations (opens in a new tab)
Fact sheets and implementation guidance from the Home Office