Under the Freedom of Information Act 2000, any person who makes a request for information to a public authority is entitled to be told in writing whether the authority holds information of the description in the request. If it does, the person is entitled to have that information communicated to them.
The Information Commission (formerly the ICO) regulates the Act. It took over the Information Commissioner's functions on 30 September 2026.
Check whether the Act covers your body
A public authority is a body, person or office listed in Schedule 1 to the Act, one designated by order under section 5, or a publicly-owned company as defined by section 6. Schedule 1 is in seven Parts: general (including government departments and the Houses of Parliament), local government, the National Health Service, maintained schools and other educational institutions, the police, other public bodies and offices, and other public bodies and offices in Northern Ireland. Parts II to V list bodies in Northern Ireland as well as in England and Wales.
The Secretary of State or the Minister for the Cabinet Office may designate by order a person not listed in Schedule 1 who appears to exercise functions of a public nature, or who provides a service under a contract with a public authority where providing it is the authority's function. Before making the order they must consult every person it relates to, or persons appearing to represent them. It cannot designate a body that an order under section 4(1) could add to Schedule 1.
Some bodies are listed in Schedule 1 only for information of a specified description. The Act then applies only to that information. A body designated under section 5 is covered only for information about the functions or contracted services named in the order.
Information is held by an authority if it holds it otherwise than on behalf of another person, or another person holds it on the authority's behalf.
Requests for environmental information are handled under the Environmental Information Regulations 2004.
Check the request is valid
A request for information must be in writing, state the applicant's name and an address for correspondence, and describe the information requested. Electronic text counts as writing if it is received in legible form and can be used for subsequent reference.
Tell the requester and provide the information
On a valid request you must tell the requester in writing whether you hold the information and, if you do, communicate it. If the applicant states, when making the request, a preference for a copy, a reasonable opportunity to inspect a record, or a digest or summary, you must so far as reasonably practicable give effect to that preference. If that is not reasonably practicable, you must tell the applicant why. If the request is for a dataset you hold, or part of one, and the requester asks in the request for an electronic copy, you must provide it, so far as reasonably practicable, in an electronic form capable of re-use. The duty is subject to the exemptions, the fees provisions, the cost limit and the rules on vexatious and repeated requests.
The duty covers the information held when the request is received. You may take account of a later amendment or deletion only if it would have been made regardless of the request. If you reasonably require further information to identify and locate what is asked for, and you have told the applicant so, you are not obliged to comply until it is supplied.
You must provide advice and assistance, so far as it would be reasonable to expect you to do so, to people who propose to make requests and to people who have made them. If you conform with the code of practice issued under section 45 in a case, you are taken to comply with this duty in that case.
Reply within 20 working days
You must comply promptly and in any event not later than the twentieth working day following the date of receipt. Promptly is the standard, and 20 working days is the outer limit. The date of receipt is the day you receive the request or, if later, the day you receive the further information you asked for. The count starts with the following working day. A working day is any day other than a Saturday, a Sunday, Christmas Day, Good Friday or a bank holiday in any part of the United Kingdom.
These change the deadline:
- if you gave a fees notice and the fee is paid within three months, the working days from the day the notice is given to the day you receive the fee are disregarded
- the Minister for the Cabinet Office may by regulations provide for a later day, not later than the sixtieth working day following the date of receipt, and may prescribe different days in different cases; regulations of this kind apply to some authorities
Some information may fall within a qualified exemption, so that only the public interest test is left to decide. You need not communicate that information until a time that is reasonable in the circumstances. The same applies to confirming or denying, where a qualified exclusion of that duty applies and only the public interest test is left. This does not extend the time for giving the refusal notice.
Charge a fee or refuse on cost
You may, within the period for complying with the duty to tell and communicate, give the applicant a written notice stating a fee to be charged for complying. If the fee is not paid within three months beginning with the day the notice is given, you are not obliged to comply.
A fee cannot exceed the total costs you reasonably expect to incur in informing the requester whether you hold the information and in communicating it, such as reproducing documents and postage, but not staff time. Where another enactment fixes the fee for disclosing the information, the fee is not set this way.
You are not obliged to comply if you estimate that the cost would exceed the appropriate limit: £600 for an authority listed in Part I of Schedule 1, which includes, for example, government departments and the Houses of Parliament, and £450 for any other public authority. In the estimate you may take account only of the costs of determining whether you hold the information, locating it, retrieving it and extracting it. Staff time is estimated at £25 per person per hour. Requests are added together for the estimate if they come from one person, or from different persons who appear to be acting in concert or in pursuance of a campaign. They must relate, to any extent, to the same or similar information and be received within 60 consecutive working days.
Even over the limit, you must still confirm or deny whether you hold the information, unless the estimated cost of doing that alone would exceed the limit.
Refuse a vexatious or repeated request
You are not obliged to comply with a request if it is vexatious. The Act does not define vexatious.
Where you have previously complied with a request, you are not obliged to comply with a subsequent identical or substantially similar request from the same person. This does not apply once a reasonable interval has elapsed between complying with the earlier request and the making of the later one. The Act does not define a reasonable interval, and the rule does not stop a different person asking for the same information.
Apply an exemption
Only the provisions listed in section 2(3) confer absolute exemption. Every other exemption in Part II is qualified. For a qualified exemption, the duty to disclose does not apply if the public interest in maintaining the exemption outweighs the public interest in disclosing the information. The same test applies to a qualified exclusion of the duty to confirm or deny.
Give a refusal notice
If you rely on an exemption, or on an exclusion of the duty to confirm or deny, you must within the time for complying give the applicant a notice. It must state that fact, specify the exemption and, if it would not otherwise be apparent, state why it applies. If you rely on the cost limit or the rule on vexatious or repeated requests, a notice stating that fact is due within the same time. You need not give it where you rely on the vexatious request rule, gave a notice on a previous request saying so, and it would in all the circumstances be unreasonable to expect a further notice.
For a qualified exemption, or a qualified exclusion of the duty to confirm or deny, you must also state your reasons for the public interest balance, in the notice or in a separate notice within a reasonable time. If you have not yet decided, the notice must say so and estimate the date. You are not obliged to state why an exemption applies, or give those reasons, to the extent that the statement would itself disclose exempt information.
Each of these notices must contain particulars of any procedure you provide for dealing with complaints about the handling of requests, or state that you provide none. It must also contain particulars of the right to complain to the Commission under section 50.
Adopt a publication scheme
Every public authority must adopt and maintain a publication scheme approved by the Commission, publish information in accordance with it, and review it from time to time. The scheme must specify the classes of information published, how, and whether it is free or paid for. It must require you to publish any dataset you hold that a person has requested, and any updated version you hold, unless you are satisfied that publishing it is not appropriate. A dataset you publish under that requirement must, where reasonably practicable, be in an electronic form capable of re-use. Further rules govern re-use of a copyright work in a dataset.
In adopting or reviewing the scheme you must have regard to the public interest in allowing public access to information you hold and in publishing the reasons for your decisions. You must publish the scheme in such manner as you think fit.
If you adopt, without modification, a model scheme the Commission has approved for authorities of your kind, no further approval is required while it remains approved.
Handle disputes and internal reviews
The section 45 code of practice is guidance and not law. Best practice under it is for each authority to have a procedure for disputes about its handling of requests, usually run as an internal review. The Act does not require one. It is usual practice to accept a request for internal review made within 40 working days of the initial response, and you are not obliged to accept a later one. A review should normally be answered within 20 working days. For a complex review, best practice is no more than a further 20 working days.
Handle a complaint to the Commission
Any person may apply to the Commission for a decision whether their request was dealt with in accordance with Part I of the Act. The Commission must make a decision unless it appears that:
- the complainant has not exhausted any complaints procedure you provide in conformity with the code of practice
- there has been undue delay in making the application (the Act sets no other deadline)
- the application is frivolous or vexatious
- the application has been withdrawn or abandoned
The Commission may decide that an authority failed to communicate information or confirm or deny when required to by section 1(1), or failed to comply with section 11 or 17. If so, its decision notice must specify the steps the authority must take and the period for taking them. That period cannot expire before the time for appealing ends. If an appeal is brought, no step affected by it need be taken until it is decided or withdrawn.
The complainant or the authority may appeal a decision notice to the Tribunal. A notice of appeal must reach the First-tier Tribunal within 28 days of the date the decision notice was sent.
If an authority fails to comply with so much of a decision notice as requires steps to be taken, the Commission may certify that failure in writing to the court. The court may then deal with the authority as if it had committed a contempt of court. The same applies to an information notice or an enforcement notice from the Commission. The court is the High Court or, in Scotland, the Court of Session. The Commission itself cannot fine an authority for failing to comply with the Act.
Legal basis
Primary legislation and key regulations