The A160/A180 (Port of Immingham Improvement) Development Consent Order 2015
At a glance
What this Act requires
Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.
Schedules
Browse 73 other Schedules — structural / supplementary
Water vole, badgers and bat roosts
(1) No part of the authorised development may be brought...
Traffic management
Detailed design
No part of the authorised development is to be brought...
The authorised development must be carried out in accordance with...
Surface and foul water drainage
Approvals and amendments to approved details
Time limits
Construction Environmental Management Plan
Landscaping
Implementation and maintenance of landscaping
Fencing
Contaminated land and groundwater
Archaeology
Ecological management plan
The enactments for the time being in force with respect...
(1) Without limitation on the scope of paragraph 1, the...
(1) The 1965 Act has effect with the modifications necessary...
For section 7 of the 1965 Act (measure of compensation)...
For section 8 of the 1965 Act (provisions as to...
The following provisions of the 1965 Act (which state the...
Section 11 (powers of entry) of the 1965 Act is...
Section 20 (protection for interests of tenants at will, etc.)...
Section 22 of the 1965 Act (interests omitted from purchase)...
For the protection of the undertakers referred to in this...
(1) Subject to the following provisions of this paragraph, the...
(1) Subject to sub-paragraphs (2) and (3), if by reason...
Where in consequence of the proposed construction of any of...
Nothing in this Part of this Schedule affects the provisions...
For the protection of Anglian Water, the following provisions have...
In this Part of this Schedule— “apparatus” means any works,...
The Secretary of State must not interfere with, build over...
The alteration, extension, removal or re-location of any apparatus must...
In the situation, where in exercise of the powers conferred...
Regardless of any provision in this Order or anything shown...
In this Part of this Schedule— “alternative apparatus” means alternative...
If in consequence of the exercise of the powers conferred...
If in consequence of the exercise of the powers conferred...
If for any reason or in consequence of the construction...
The following provisions of this Part of this Schedule have...
In this Part of this Schedule— “construction” includes execution, placing,...
(1) Where under this Part of this Schedule Network Rail...
(1) The Secretary of State must not exercise the powers...
(1) The Secretary of State must, before commencing construction of...
(1) Any specified work and any protective works to be...
The Secretary of State must— (a) at all times afford...
This Part of this Schedule does not apply to apparatus...
Network Rail must at all reasonable times afford reasonable facilities...
(1) If any permanent or temporary alterations or additions to...
The Secretary of State must repay to Network Rail all...
(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
If at any time after the completion of a specified...
The Secretary of State must not provide any illumination or...
Any additional expenses which Network Rail may reasonably incur in...
(1) The Secretary of State must pay to Network Rail...
Network Rail must, on receipt of a request from the...
In the assessment of any sums payable to Network Rail...
(1) Where any street is stopped up under article 12...
The Secretary of State and Network Rail may, subject in...
Nothing in this Order, or in any enactment incorporated with...
The Secretary of State must give written notice to Network...
The Secretary of State must no later than 28 days...
For the protection of any operator, the following provisions have...
In this Part of this Schedule— “the 2003 Act” means...
The exercise of the powers conferred by article 37 (statutory...
(1) Subject to sub-paragraphs (2) to (4), if as the...
The Secretary of State, in the case of the powers...
Regardless of any provision in this Order or anything shown...
(1) If, in the exercise of the powers conferred by...
(1) Where, in accordance with the provisions of this Part...
(1) Not less than 28 days before starting the execution...
Browse 41 other sections — procedural / definitional / commencement
Citation and commencement
Interpretation
Development consent
Maintenance of authorised development
Limits of deviation
Benefit of Order
Consent to transfer benefit of Order
Application and modification of legislative provisions
Application of the
Construction and maintenance of new, altered or diverted streets
Classification of roads, etc.
Permanent stopping up and restriction of use of streets
Temporary stopping up and restriction of use of streets
Access to works
Clearways
Discharge of water
Protective work to buildings
Authority to survey and investigate land
Compulsory acquisition of land
Compulsory acquisition of land – incorporation of the mineral code
Time limit for exercise of authority to acquire land compulsorily
Compulsory acquisition of rights
Private rights over land
Application of the Compulsory Purchase (Vesting Declarations) Act 1981
Acquisition of subsoil or air-space only
Acquisition of part of certain properties
Rights under or over streets
Temporary use of land for carrying out the authorised development
Temporary use of land for maintaining the authorised development
Statutory undertakers
Apparatus and rights of statutory undertakers in stopped up streets
Recovery of costs of new connections
Felling or lopping of trees
Application of landlord and tenant law
Operational land for purposes of the
Defence to proceedings in respect of statutory nuisance
Protection of interests
Certification of plans, etc.
Service of notices
Arbitration
Traffic regulation