- Status
- In Force
What it defines
Regulations creating concrete business duties or carrying penalties, grouped as the instrument is structured. Titles link to the source text — blue means you’re leaving for legislation.gov.uk.
60 other provisions — procedural and definitional
s.art001
Citation
s.art002
Interpretation
s.art003
Incorporation of the 1847 Act
s.art004
Modification of enactments
s.art005
Development consent etc. granted by the Order
s.art006
Limits of deviation
s.art007
Period for completion of work
s.art008
Jurisdiction of the Harbour Authority
s.art009
Agreements entered into by the Company etc.
s.art010
Maintenance of authorised development
s.art011
Provision of works
s.art012
Benefit of Order
s.art013
Consent to transfer benefit of Order
s.art014
Guarantees in respect of payment
s.art015
Street works
s.art016
Temporary stopping up of streets
s.art017
Access to works
s.art018
Agreements with street authorities
s.art019
Public rights of way
s.art020
Discharge of water
s.art021
Protective work to buildings
s.art022
Authority to survey and investigate the land
s.art023
Tidal works not to be executed without approval of Secretary of State
s.art024
Abatement of works abandoned or decayed
s.art025
Survey of tidal works
s.art026
Lights on tidal works etc. during construction
s.art027
Provision against danger to navigation
s.art028
Permanent lights on tidal works
s.art029
Power to appropriate
s.art030
Compulsory acquisition of land
s.art031
Power to override easements and other rights
s.art032
Compulsory acquisition of land – incorporation of the mineral code
s.art033
Time limit for exercise of authority to acquire land compulsorily
s.art034
Compulsory acquisition of rights
s.art035
Private rights of way
s.art036
Application of the Compulsory Purchase (Vesting Declarations) Act 1981
s.art037
Acquisition of subsoil only
s.art038
Acquisition of part of certain properties
s.art039
Rights under or over streets
s.art040
Temporary use of land for carrying out the authorised development
s.art041
Temporary use of land for maintaining authorised development
s.art042
Statutory undertakers
s.art043
Recovery of costs of new connections
s.art044
Deemed marine licence
s.art045
Felling or lopping of trees
s.art046
Trees subject to tree preservation orders
s.art047
Railway and navigation undertakings
s.art048
Arrangements with Her Majesty’s Revenue and Customs
s.art049
Application of landlord and tenant law
s.art050
Operational land for purposes of the 1990 Act
s.art051
Defence to proceedings in respect of statutory nuisance
s.art052
Protection of interests
s.art053
Saving for Trinity House
s.art054
Planning etc. jurisdiction
s.art055
Certification of plans etc
s.art055
Certification of further environmental documents
s.art055
Certification of additional plans etc.
s.art056
Service of notices
s.art057
Arbitration
s.art058
Requirements - appeals
Schedules
Schedules
0 of 246 shown246 other schedules
s.sch001
In the district of North Lincolnshire— Work No. 1—a quay...
s.sch001
In the district of North Lincolnshire— Work No. 2— improvement...
s.sch001
In the district of North Lincolnshire and within the Order...
s.sch001
In the district of the East Riding of Yorkshire and...
s.sch001
In the district of North Lincolnshire ecological mitigation works in...
s.sch008
(1) In this Schedule:— “the 2009 Act” means the Marine...
s.sch008
(1) The licence holder is permitted to deposit temporary bog...
s.sch008
(1) The licence holder is permitted to carry out capital...
s.sch008
(1) The licence holder is permitted to carry out maintenance...
s.sch008
Any breach of this Schedule does not constitute a breach...
s.sch008
(1) The conditions set out at paragraphs 15 to 69...
s.sch008
(1) No licensed activities are to be carried out until...
s.sch008
No licensed activity is to be carried out until 4...
s.sch008
The MMO must be notified by the licence holder at...
s.sch008
The licence holder must ensure that the MMO District Marine...
s.sch008
The MMO must be notified by the licence holder in...
s.sch008
(1) Unless otherwise advised in writing by the MMO, the...
s.sch008
The licence holder must ensure that a copy of this...
s.sch008
The licence holder must ensure that the names of vessels...
s.sch008
The licence holder must ensure that a copy of this...
s.sch008
Should the licence holder become aware that any of the...
s.sch008
The works must be carried out in accordance with a...
s.sch008
(1) The following dependencies apply to the licensed activities in...
s.sch008
The licence holder must ensure that any coatings and treatments...
s.sch008
(1) The licence holder must only work and access the...
s.sch008
The licence holder must ensure that during the works all...
s.sch008
The licence holder must ensure that any equipment, temporary structures,...
s.sch008
For the purpose of constructing and maintaining the authorised development...
s.sch008
(1) The licence holder must ensure that no waste concrete...
s.sch008
(1) Prior to any works commencing below the level of...
s.sch008
The licence holder must install bunding and storage facilities to...
s.sch008
(1) The licence holder must ensure that any oil, fuel...
s.sch008
The licence holder must ensure that a Notice to Mariners...
s.sch008
The licence holder must ensure that all materials used in...
s.sch008
(1) The licence holder must ensure that a protocol for...
s.sch008
(1) No operations consisting of piling are to commence until...
s.sch008
No operations consisting of piling are to commence until a...
s.sch008
(1) No development is to be commenced until an active...
s.sch008
(1) The licence holder is permitted to construct the quay...
s.sch008
No percussive piling is to take place between 7th April...
s.sch008
(1) Percussive piling is to be restricted at other times...
s.sch008
No percussive piling is to take place before 0600 hours...
s.sch008
The maximum diameter of marine piles is to be 2.1...
s.sch008
Conditions 32 to 69 apply to licensed activities consisting of...
s.sch008
(1) The licence holder must agree a dredge and disposal...
s.sch008
The licence holder must ensure that— (a) as a result...
s.sch008
(1) The licence holder must ensure that certified returns of...
s.sch008
(1) The licence holder must ensure that dredged material is...
s.sch008
Should disposal of material be found to be the cause...
s.sch008
(1) The licence holder is permitted to construct and remove...
s.sch008
The licence holder must ensure that during the course of...
s.sch008
The licence holder must undertake regular bathymetric surveys to ensure...
s.sch008
(1) The licence holder must ensure that no gravel is...
s.sch008
The licence holder must ensure that during the course of...
s.sch008
(1) The licence holder must employ methods to minimise resuspension...
s.sch008
(1) The licence holder must undertake sampling and chemical analysis...
s.sch008
The licence holder must ensure that during the course of...
s.sch008
(1) The licence holder must monitor disposal site HU080 to...
s.sch008
(1) The licence holder must notify the Conservancy Authority of...
s.sch008
The berthing pocket must be maintained to no deeper than...
s.sch008
Following or during the dredging of the berthing pocket, the...
s.sch008
(1) The licence holder must employ methods to minimise resuspension...
s.sch008
(1) Any rock or gravel material to be placed within...
s.sch008
Any rock armour surplus to that specified in paragraph 4(1)(b)...
s.sch008
Any rock or gravel surplus to that specified in paragraph...
s.sch008
(1) The licence holder must ensure that a full method...
s.sch008
The licence holder must ensure that pre-works and post-works trawl...
s.sch008
(1) The licence holder must ensure that any vessels used...
s.sch008
The licence holder must ensure that sea-going tug or tugs...
s.sch008
Subject to paragraph 69, the licence holder must ensure that...
s.sch008
Any rock that is misplaced or lost below mean high...
s.sch008
(1) The licence holder is permitted to construct a pumping...
s.sch008
The licence holder is permitted to remove a 250 metre...
s.sch008
The licence holder is permitted to deposit rock armouring to...
s.sch009
In this Part of this Schedule— “authorised works” means any...
s.sch009
In addition to any requirement under articles 26 (lights on...
s.sch009
(1) For the protection of Anglian Water, the following provisions,...
s.sch009
The undertaker must not interfere with, build over or near...
s.sch009
The alteration, extension, removal or re-location of any apparatus must...
s.sch009
In the situation where, in exercise of the powers conferred...
s.sch009
Regardless of any provision in this Order or anything shown...
s.sch009
If in consequence of the exercise of the powers conferred...
s.sch009
If for any reason or in consequence of the construction...
s.sch009
The undertaker must only exercise its powers of compulsory acquisition...
s.sch009
Before interfering with or extinguishing any existing rights forBethany Jayne...
s.sch009
(1) For the protection of Royal Mail Group Ltd (‘Royal...
s.sch009
On completion of the construction of any part of a...
s.sch009
Any dispute arising between the undertaker and Royal Mail Group...
s.sch009
In this Part of this Schedule— “AB Ports” means Associated...
s.sch009
The provisions of this Part of this Schedule, unless otherwise...
s.sch009
(1) If— (a) during the construction of a tidal work...
s.sch009
In exercising the powers conferred by this Order to construct...
s.sch009
If AB Ports secures access between parcels 03009, 03014 and...
s.sch009
The undertaker, before carrying out any works or exercising the...
s.sch009
(1) The undertaker must pay to ABP Ports all costs,...
s.sch009
Any difference arising between the undertaker and AB Ports under...
s.sch009
(1) Unless agreed otherwise in writing between the undertaker and...
s.sch009
(1) If any tidal work— (a) is constructed otherwise than...
s.sch009
Before extinguishing any existing rights for the Oil and Pipelines...
s.sch009
Application
s.sch009
Interpretation
s.sch009
Regulation of powers over Rosper Road
s.sch009
(1) The undertaker must not exercise the powers under any...
s.sch009
Insofar as the construction of the OCGT authorised development is...
s.sch009
Arbitration
s.sch009
(1) If any tidal work or any other work of...
s.sch009
(1) The Harbour Authority must not in the exercise of...
s.sch009
(1) Before the commencement of construction of the first tidal...
s.sch009
(1) This paragraph applies if any part of the river...
s.sch009
(1) The Harbour Authority is responsible for and must make...
s.sch009
(1) Before exercising the powers conferred by article 22 (authority...
s.sch009
(1) Subject to article 4(1) (modification of enactments) and this...
s.sch009
(1) The provisions of this Part of this Schedule, unless...
s.sch009
Before commencing harbour operations the Harbour Authority must submit to...
s.sch009
(1) Subject to any agreement concluded between the Harbour Authority,...
s.sch009
(1) Before exercising any power under section 252 of the...
s.sch009
Within 14 days after the date of any transfer or...
s.sch009
The Harbour Authority must consult the harbour master before submitting...
s.sch009
Any dispute arising between the Harbour Authority and the Conservancy...
s.sch009
The following provisions apply for the protection of the Environment...
s.sch009
The authorised development must be carried out in a way...
s.sch009
The requirements set out in the Agency’s Pollution Prevention Guideline...
s.sch009
On completion of the works, all debris and surplus material...
s.sch009
(1) Before— (a) submitting any plans and sections for any...
s.sch009
The undertaker must bring the conditions contained in paragraphs 27...
s.sch009
For the protection of the Highways Agency, no part of...
s.sch009
For the protection of Network Rail, the following provisions, unless...
s.sch009
In this Part of this Schedule— “the engineer” means an...
s.sch009
(1) Where under this Part of this Schedule Network Rail...
s.sch009
(1) The undertaker must not exercise the powers conferred by...
s.sch009
(1) The undertaker, before commencing construction of any specified work,...
s.sch009
(1) Any specified work and any protective works to be...
s.sch009
The undertaker must— (a) at all times afford reasonable facilities...
s.sch009
Network Rail must at all times afford reasonable facilities to...
s.sch009
When submitting any document specified in the Table in paragraph...
s.sch009
(1) If any permanent or temporary alterations or additions to...
s.sch009
The undertaker must repay to Network Rail all fees, costs,...
s.sch009
If at any time after the completion of a specified...
s.sch009
Any additional expenses which Network Rail may reasonably and properly...
s.sch009
(1) The undertaker must pay to Network Rail all costs,...
s.sch009
Network Rail, on receipt of a request from the undertaker,...
s.sch009
In the assessment of any sums payable to Network Rail...
s.sch009
The undertaker, no later than 28 days from the date...
s.sch009
For the protection of C.GEN the following provisions, unless otherwise...
s.sch009
The undertaker must not in the exercise of the powers...
s.sch009
Any operations for the construction of any tidal work approved...
s.sch009
The construction and operation of the authorised development must not...
s.sch009
The undertaker must not in the exercise of the powers...
s.sch009
The construction and operation of the authorised development must not...
s.sch009
With the exception of any duty owed by C.GEN to...
s.sch009
Unless otherwise agreed in writing, any dispute arising between the...
s.sch009
(1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch009
For the protection of C.RO the following provisions, unless otherwise...
s.sch009
In this Part of this Schedule— “HST” means the harbour...
s.sch009
(1) Before— (a) submitting any plans and sections for any...
s.sch009
Any operations for the construction of any tidal work approved...
s.sch009
(1) The Harbour Authority must not without the consent of...
s.sch009
The Harbour Authority must not in the exercise of the...
s.sch009
The undertaker must pay to C.RO the reasonable costs incurred...
s.sch009
The undertaker must afford to C.RO such facilities as C.RO...
s.sch009
The undertaker must provide and maintain on any tidal works...
s.sch009
After the purpose of any temporary tidal work in or...
s.sch009
If any tidal work is abandoned or falls into decay...
s.sch009
(1) The undertaker must not allow vessels associated with the...
s.sch009
(1) The undertaker must not dredge in the HST approach...
s.sch009
The undertaker must not in the exercise of the powers...
s.sch009
The construction and operation of the authorised development must not...
s.sch009
The Harbour Authority must not, in exercise of the powers...
s.sch009
The undertaker must not in the exercise of the powers...
s.sch009
The construction and operation of the authorised development must not...
s.sch009
(1) C.RO may recover from the undertaker any reasonable expenses...
s.sch009
(1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch009
With the exception of any duty owed by C.RO to...
s.sch009
Unless otherwise agreed in writing, any dispute arising between the...
s.sch009
In this Part of this Schedule— “P66” means Phillips 66...
s.sch009
Before commencing any part of the authorised development or the...
s.sch009
No works comprising any part of the authorised development or...
s.sch009
Any approval of P66 required under paragraph 78 must not...
s.sch009
If any pile, stump or other obstruction to navigation becomes...
s.sch009
In this Part of this Schedule— “apparatus” means— in the...
s.sch009
For the protection of National Grid the following provisions, unless...
s.sch009
(1) Not less than 56 days before commencing the execution...
s.sch009
Subject to the following provisions of this paragraph, the undertaker...
s.sch009
(1) Subject to sub-paragraphs (2) and (3), if by reason...
s.sch009
Nothing in this Part of this Schedule affects the provisions...
s.sch009
If in consequence of the exercise of any powers under...
s.sch009
Any dispute arising between the undertaker and National Grid under...
s.sch009
In this Part of this Schedule— “the outfall and intake”...
s.sch009
For the protection of E.ON the following provisions, unless otherwise...
s.sch009
If— (a) by reason of the construction of any tidal...
s.sch009
Before extinguishing any existing rights for E.ON to keep, inspect,...
s.sch009
(1) No stage of the authorised development is to commence...
s.sch009
Any dispute arising between the undertaker and E.ON under this...
s.sch009
For the protection of Centrica the following provisions, unless otherwise...
s.sch009
In this Part of this Schedule, “the pipelines” means Centrica’s...
s.sch009
Before extinguishing any existing rights for Centrica to keep, inspect,...
s.sch009
(1) No stage of the authorised development is to commence...
s.sch009
Before extinguishing any existing rights for Centrica to pass along...
s.sch009
The undertaker must not make use of the power station...
s.sch009
Any dispute arising between the undertaker and Centrica under this...
s.sch010
The limits of the harbour are the boundaries of the...
s.sch011
In this Schedule— “environmental statement” means the statement submitted under...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) The authorised development must not commence until a monitoring...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) The authorised development must not commence until the compensation...
s.sch011
The authorised development must be begun within 7 years of...
s.sch011
The compensation environmental management and monitoring plan, marine environmental management...
s.sch011
(1) The undertaker must not commence construction of the quay...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) No stage of the authorised development consisting of the...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) The authorised development must not be brought into use...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
(1) No stage of the of the authorised development is...
s.sch011
No part of the authorised development is to commence until...
s.sch011
(1) No stage of the of the authorised development is...
s.sch011
(1) No stage of the authorised development is to commence...
s.sch011
No stage of the authorised development is to commence until...
s.sch011
(1) No building of the authorised development is to be...
s.sch011
No stage of the authorised development is to commence until...
s.sch011
No structure is to be erected over 45 metres in...
s.sch011
(1) No development is to commence until a scheme for...
s.sch011
For any piling that is to take place above high...
s.sch011
(1) No development is to commence until a scheme for...
s.sch011
(1) No development is to commence until a scheme for...
s.sch011
(1) The cargo for which the authorised development is authorised...
s.sch011
(1) Prior to the commencement of the relevant stage of...
s.sch011
(1) Prior to carrying out the licensed activity referred to...
s.sch011
(1) During the construction and operation of the authorised development,...
s.sch011
(1) Following construction of the new flood defence embankment at...
s.sch011
(1) No development is to commence until the detailed design...
s.sch011
Where under any of the above requirements the approval or...
s.sch011
Except where the authorised development is carried out in accordance...
s.sch011
The authorised development must be carried out in accordance with...
s.sch011
No stage of the authorised development, other than tidal works,...
s.sch011
(1) All landscaping works must be carried out in accordance...
s.sch011
No stage of the authorised development, other than tidal works,...
Duty extraction and severity labels are Guvnor’s analysis of the instrument, not the instrument itself. Always verify against the linked source text.