UK Statutory Instrument 2014 United Kingdom

The Able Marine Energy Park Development Consent Order 2014

At a glance

What this Act requires

Sections that create concrete duties on businesses or carry penalties. Procedural and definitional sections are folded into the “Browse other sections” expander at the bottom of each group. Click any section title to read the source text on legislation.gov.uk.

Schedules

Browse 246 other Schedules — structural / supplementary
s.sch001

In the district of North Lincolnshire— Work No. 1—a quay...

s.sch001

In the district of North Lincolnshire— Work No. 2— improvement...

s.sch001

In the district of North Lincolnshire and within the Order...

s.sch001

In the district of the East Riding of Yorkshire and...

s.sch001

In the district of North Lincolnshire ecological mitigation works in...

s.sch008

(1) In this Schedule:— “the 2009 Act” means the Marine...

s.sch008

(1) The licence holder is permitted to deposit temporary bog...

s.sch008

(1) The licence holder is permitted to carry out capital...

s.sch008

(1) The licence holder is permitted to carry out maintenance...

s.sch008

Any breach of this Schedule does not constitute a breach...

s.sch008

(1) The conditions set out at paragraphs 15 to 69...

s.sch008

(1) No licensed activities are to be carried out until...

s.sch008

No licensed activity is to be carried out until 4...

s.sch008

The MMO must be notified by the licence holder at...

s.sch008

The licence holder must ensure that the MMO District Marine...

s.sch008

The MMO must be notified by the licence holder in...

s.sch008

(1) Unless otherwise advised in writing by the MMO, the...

s.sch008

The licence holder must ensure that a copy of this...

s.sch008

The licence holder must ensure that the names of vessels...

s.sch008

The licence holder must ensure that a copy of this...

s.sch008

Should the licence holder become aware that any of the...

s.sch008

The works must be carried out in accordance with a...

s.sch008

(1) The following dependencies apply to the licensed activities in...

s.sch008

The licence holder must ensure that any coatings and treatments...

s.sch008

(1) The licence holder must only work and access the...

s.sch008

The licence holder must ensure that during the works all...

s.sch008

The licence holder must ensure that any equipment, temporary structures,...

s.sch008

For the purpose of constructing and maintaining the authorised development...

s.sch008

(1) The licence holder must ensure that no waste concrete...

s.sch008

(1) Prior to any works commencing below the level of...

s.sch008

The licence holder must install bunding and storage facilities to...

s.sch008

(1) The licence holder must ensure that any oil, fuel...

s.sch008

The licence holder must ensure that a Notice to Mariners...

s.sch008

The licence holder must ensure that all materials used in...

s.sch008

(1) The licence holder must ensure that a protocol for...

s.sch008

(1) No operations consisting of piling are to commence until...

s.sch008

No operations consisting of piling are to commence until a...

s.sch008

(1) No development is to be commenced until an active...

s.sch008

(1) The licence holder is permitted to construct the quay...

s.sch008

No percussive piling is to take place between 7th April...

s.sch008

(1) Percussive piling is to be restricted at other times...

s.sch008

No percussive piling is to take place before 0600 hours...

s.sch008

The maximum diameter of marine piles is to be 2.1...

s.sch008

Conditions 32 to 69 apply to licensed activities consisting of...

s.sch008

(1) The licence holder must agree a dredge and disposal...

s.sch008

The licence holder must ensure that— (a) as a result...

s.sch008

(1) The licence holder must ensure that certified returns of...

s.sch008

(1) The licence holder must ensure that dredged material is...

s.sch008

Should disposal of material be found to be the cause...

s.sch008

(1) The licence holder is permitted to construct and remove...

s.sch008

The licence holder must ensure that during the course of...

s.sch008

The licence holder must undertake regular bathymetric surveys to ensure...

s.sch008

(1) The licence holder must ensure that no gravel is...

s.sch008

The licence holder must ensure that during the course of...

s.sch008

(1) The licence holder must employ methods to minimise resuspension...

s.sch008

(1) The licence holder must undertake sampling and chemical analysis...

s.sch008

The licence holder must ensure that during the course of...

s.sch008

(1) The licence holder must monitor disposal site HU080 to...

s.sch008

(1) The licence holder must notify the Conservancy Authority of...

s.sch008

The berthing pocket must be maintained to no deeper than...

s.sch008

Following or during the dredging of the berthing pocket, the...

s.sch008

(1) The licence holder must employ methods to minimise resuspension...

s.sch008

(1) Any rock or gravel material to be placed within...

s.sch008

Any rock armour surplus to that specified in paragraph 4(1)(b)...

s.sch008

Any rock or gravel surplus to that specified in paragraph...

s.sch008

(1) The licence holder must ensure that a full method...

s.sch008

The licence holder must ensure that pre-works and post-works trawl...

s.sch008

(1) The licence holder must ensure that any vessels used...

s.sch008

The licence holder must ensure that sea-going tug or tugs...

s.sch008

Subject to paragraph 69, the licence holder must ensure that...

s.sch008

Any rock that is misplaced or lost below mean high...

s.sch008

(1) The licence holder is permitted to construct a pumping...

s.sch008

The licence holder is permitted to remove a 250 metre...

s.sch008

The licence holder is permitted to deposit rock armouring to...

s.sch009

In this Part of this Schedule— “authorised works” means any...

s.sch009

In addition to any requirement under articles 26 (lights on...

s.sch009

(1) For the protection of Anglian Water, the following provisions,...

s.sch009

The undertaker must not interfere with, build over or near...

s.sch009

The alteration, extension, removal or re-location of any apparatus must...

s.sch009

In the situation where, in exercise of the powers conferred...

s.sch009

Regardless of any provision in this Order or anything shown...

s.sch009

If in consequence of the exercise of the powers conferred...

s.sch009

If for any reason or in consequence of the construction...

s.sch009

The undertaker must only exercise its powers of compulsory acquisition...

s.sch009

Before interfering with or extinguishing any existing rights forBethany Jayne...

s.sch009

(1) For the protection of Royal Mail Group Ltd (‘Royal...

s.sch009

On completion of the construction of any part of a...

s.sch009

Any dispute arising between the undertaker and Royal Mail Group...

s.sch009

In this Part of this Schedule— “AB Ports” means Associated...

s.sch009

The provisions of this Part of this Schedule, unless otherwise...

s.sch009

(1) If— (a) during the construction of a tidal work...

s.sch009

In exercising the powers conferred by this Order to construct...

s.sch009

If AB Ports secures access between parcels 03009, 03014 and...

s.sch009

The undertaker, before carrying out any works or exercising the...

s.sch009

(1) The undertaker must pay to ABP Ports all costs,...

s.sch009

Any difference arising between the undertaker and AB Ports under...

s.sch009

(1) Unless agreed otherwise in writing between the undertaker and...

s.sch009

(1) If any tidal work— (a) is constructed otherwise than...

s.sch009

Before extinguishing any existing rights for the Oil and Pipelines...

s.sch009

Application

s.sch009

Interpretation

s.sch009

Regulation of powers over Rosper Road

s.sch009

(1) The undertaker must not exercise the powers under any...

s.sch009

Insofar as the construction of the OCGT authorised development is...

s.sch009

Arbitration

s.sch009

(1) If any tidal work or any other work of...

s.sch009

(1) The Harbour Authority must not in the exercise of...

s.sch009

(1) Before the commencement of construction of the first tidal...

s.sch009

(1) This paragraph applies if any part of the river...

s.sch009

(1) The Harbour Authority is responsible for and must make...

s.sch009

(1) Before exercising the powers conferred by article 22 (authority...

s.sch009

(1) Subject to article 4(1) (modification of enactments) and this...

s.sch009

(1) The provisions of this Part of this Schedule, unless...

s.sch009

Before commencing harbour operations the Harbour Authority must submit to...

s.sch009

(1) Subject to any agreement concluded between the Harbour Authority,...

s.sch009

(1) Before exercising any power under section 252 of the...

s.sch009

Within 14 days after the date of any transfer or...

s.sch009

The Harbour Authority must consult the harbour master before submitting...

s.sch009

Any dispute arising between the Harbour Authority and the Conservancy...

s.sch009

The following provisions apply for the protection of the Environment...

s.sch009

The authorised development must be carried out in a way...

s.sch009

The requirements set out in the Agency’s Pollution Prevention Guideline...

s.sch009

On completion of the works, all debris and surplus material...

s.sch009

(1) Before— (a) submitting any plans and sections for any...

s.sch009

The undertaker must bring the conditions contained in paragraphs 27...

s.sch009

For the protection of the Highways Agency, no part of...

s.sch009

For the protection of Network Rail, the following provisions, unless...

s.sch009

In this Part of this Schedule— “the engineer” means an...

s.sch009

(1) Where under this Part of this Schedule Network Rail...

s.sch009

(1) The undertaker must not exercise the powers conferred by...

s.sch009

(1) The undertaker, before commencing construction of any specified work,...

s.sch009

(1) Any specified work and any protective works to be...

s.sch009

The undertaker must— (a) at all times afford reasonable facilities...

s.sch009

Network Rail must at all times afford reasonable facilities to...

s.sch009

When submitting any document specified in the Table in paragraph...

s.sch009

(1) If any permanent or temporary alterations or additions to...

s.sch009

The undertaker must repay to Network Rail all fees, costs,...

s.sch009

If at any time after the completion of a specified...

s.sch009

Any additional expenses which Network Rail may reasonably and properly...

s.sch009

(1) The undertaker must pay to Network Rail all costs,...

s.sch009

Network Rail, on receipt of a request from the undertaker,...

s.sch009

In the assessment of any sums payable to Network Rail...

s.sch009

The undertaker, no later than 28 days from the date...

s.sch009

For the protection of C.GEN the following provisions, unless otherwise...

s.sch009

The undertaker must not in the exercise of the powers...

s.sch009

Any operations for the construction of any tidal work approved...

s.sch009

The construction and operation of the authorised development must not...

s.sch009

The undertaker must not in the exercise of the powers...

s.sch009

The construction and operation of the authorised development must not...

s.sch009

With the exception of any duty owed by C.GEN to...

s.sch009

Unless otherwise agreed in writing, any dispute arising between the...

s.sch009

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch009

For the protection of C.RO the following provisions, unless otherwise...

s.sch009

In this Part of this Schedule— “HST” means the harbour...

s.sch009

(1) Before— (a) submitting any plans and sections for any...

s.sch009

Any operations for the construction of any tidal work approved...

s.sch009

(1) The Harbour Authority must not without the consent of...

s.sch009

The Harbour Authority must not in the exercise of the...

s.sch009

The undertaker must pay to C.RO the reasonable costs incurred...

s.sch009

The undertaker must afford to C.RO such facilities as C.RO...

s.sch009

The undertaker must provide and maintain on any tidal works...

s.sch009

After the purpose of any temporary tidal work in or...

s.sch009

If any tidal work is abandoned or falls into decay...

s.sch009

(1) The undertaker must not allow vessels associated with the...

s.sch009

(1) The undertaker must not dredge in the HST approach...

s.sch009

The undertaker must not in the exercise of the powers...

s.sch009

The construction and operation of the authorised development must not...

s.sch009

The Harbour Authority must not, in exercise of the powers...

s.sch009

The undertaker must not in the exercise of the powers...

s.sch009

The construction and operation of the authorised development must not...

s.sch009

(1) C.RO may recover from the undertaker any reasonable expenses...

s.sch009

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch009

With the exception of any duty owed by C.RO to...

s.sch009

Unless otherwise agreed in writing, any dispute arising between the...

s.sch009

In this Part of this Schedule— “P66” means Phillips 66...

s.sch009

Before commencing any part of the authorised development or the...

s.sch009

No works comprising any part of the authorised development or...

s.sch009

Any approval of P66 required under paragraph 78 must not...

s.sch009

If any pile, stump or other obstruction to navigation becomes...

s.sch009

In this Part of this Schedule— “apparatus” means— in the...

s.sch009

For the protection of National Grid the following provisions, unless...

s.sch009

(1) Not less than 56 days before commencing the execution...

s.sch009

Subject to the following provisions of this paragraph, the undertaker...

s.sch009

(1) Subject to sub-paragraphs (2) and (3), if by reason...

s.sch009

Nothing in this Part of this Schedule affects the provisions...

s.sch009

If in consequence of the exercise of any powers under...

s.sch009

Any dispute arising between the undertaker and National Grid under...

s.sch009

In this Part of this Schedule— “the outfall and intake”...

s.sch009

For the protection of E.ON the following provisions, unless otherwise...

s.sch009

If— (a) by reason of the construction of any tidal...

s.sch009

Before extinguishing any existing rights for E.ON to keep, inspect,...

s.sch009

(1) No stage of the authorised development is to commence...

s.sch009

Any dispute arising between the undertaker and E.ON under this...

s.sch009

For the protection of Centrica the following provisions, unless otherwise...

s.sch009

In this Part of this Schedule, “the pipelines” means Centrica’s...

s.sch009

Before extinguishing any existing rights for Centrica to keep, inspect,...

s.sch009

(1) No stage of the authorised development is to commence...

s.sch009

Before extinguishing any existing rights for Centrica to pass along...

s.sch009

The undertaker must not make use of the power station...

s.sch009

Any dispute arising between the undertaker and Centrica under this...

s.sch010

The limits of the harbour are the boundaries of the...

s.sch011

In this Schedule— “environmental statement” means the statement submitted under...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) The authorised development must not commence until a monitoring...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) The authorised development must not commence until the compensation...

s.sch011

The authorised development must be begun within 7 years of...

s.sch011

The compensation environmental management and monitoring plan, marine environmental management...

s.sch011

(1) The undertaker must not commence construction of the quay...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) No stage of the authorised development consisting of the...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) The authorised development must not be brought into use...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

(1) No stage of the of the authorised development is...

s.sch011

No part of the authorised development is to commence until...

s.sch011

(1) No stage of the of the authorised development is...

s.sch011

(1) No stage of the authorised development is to commence...

s.sch011

No stage of the authorised development is to commence until...

s.sch011

(1) No building of the authorised development is to be...

s.sch011

No stage of the authorised development is to commence until...

s.sch011

No structure is to be erected over 45 metres in...

s.sch011

(1) No development is to commence until a scheme for...

s.sch011

For any piling that is to take place above high...

s.sch011

(1) No development is to commence until a scheme for...

s.sch011

(1) No development is to commence until a scheme for...

s.sch011

(1) The cargo for which the authorised development is authorised...

s.sch011

(1) Prior to the commencement of the relevant stage of...

s.sch011

(1) Prior to carrying out the licensed activity referred to...

s.sch011

(1) During the construction and operation of the authorised development,...

s.sch011

(1) Following construction of the new flood defence embankment at...

s.sch011

(1) No development is to commence until the detailed design...

s.sch011

Where under any of the above requirements the approval or...

s.sch011

Except where the authorised development is carried out in accordance...

s.sch011

The authorised development must be carried out in accordance with...

s.sch011

No stage of the authorised development, other than tidal works,...

s.sch011

(1) All landscaping works must be carried out in accordance...

s.sch011

No stage of the authorised development, other than tidal works,...

Browse 60 other sections — procedural / definitional / commencement
s.art001

Citation

s.art002

Interpretation

s.art003

Incorporation of the 1847 Act

s.art004

Modification of enactments

s.art005

Development consent etc. granted by the Order

s.art006

Limits of deviation

s.art007

Period for completion of work

s.art008

Jurisdiction of the Harbour Authority

s.art009

Agreements entered into by the Company etc.

s.art010

Maintenance of authorised development

s.art011

Provision of works

s.art012

Benefit of Order

s.art013

Consent to transfer benefit of Order

s.art014

Guarantees in respect of payment

s.art015

Street works

s.art016

Temporary stopping up of streets

s.art017

Access to works

s.art018

Agreements with street authorities

s.art019

Public rights of way

s.art020

Discharge of water

s.art021

Protective work to buildings

s.art022

Authority to survey and investigate the land

s.art023

Tidal works not to be executed without approval of Secretary of State

s.art024

Abatement of works abandoned or decayed

s.art025

Survey of tidal works

s.art026

Lights on tidal works etc. during construction

s.art027

Provision against danger to navigation

s.art028

Permanent lights on tidal works

s.art029

Power to appropriate

s.art030

Compulsory acquisition of land

s.art031

Power to override easements and other rights

s.art032

Compulsory acquisition of land – incorporation of the mineral code

s.art033

Time limit for exercise of authority to acquire land compulsorily

s.art034

Compulsory acquisition of rights

s.art035

Private rights of way

s.art036

Application of the Compulsory Purchase (Vesting Declarations) Act 1981

s.art037

Acquisition of subsoil only

s.art038

Acquisition of part of certain properties

s.art039

Rights under or over streets

s.art040

Temporary use of land for carrying out the authorised development

s.art041

Temporary use of land for maintaining authorised development

s.art042

Statutory undertakers

s.art043

Recovery of costs of new connections

s.art044

Deemed marine licence

s.art045

Felling or lopping of trees

s.art046

Trees subject to tree preservation orders

s.art047

Railway and navigation undertakings

s.art048

Arrangements with Her Majesty’s Revenue and Customs

s.art049

Application of landlord and tenant law

s.art050

Operational land for purposes of the 1990 Act

s.art051

Defence to proceedings in respect of statutory nuisance

s.art052

Protection of interests

s.art053

Saving for Trinity House

s.art054

Planning etc. jurisdiction

s.art055

Certification of plans etc

s.art055

Certification of further environmental documents

s.art055

Certification of additional plans etc.

s.art056

Service of notices

s.art057

Arbitration

s.art058

Requirements - appeals

Explore more

Browse legislation