Respond to Gateway 2 rejection
What to do if your Gateway 2 application has been rejected. Covers understanding rejection reasons, your options for appeal or resubmission, and strengthening your next application.
Your Gateway 2 application has been rejected
A rejection is frustrating, but it does not mean your project cannot proceed. It means specific issues need addressing. This guide helps you understand your options and take the right next steps.
-
Understand your rejection notice
The BSR issues different responses. Check which you received:
- Rejection at validation: The application was invalid (incomplete or wrongly made) - correct and resubmit
- Request for further information: Application incomplete - provide details within the deadline
- Grant subject to requirements: Approved, but with requirements you must meet
- Refusal: Formally refused - submit a new application, or request a review and then appeal
Common rejection reasons
- Incomplete fire safety strategy
- Inadequate competence evidence for duty holders
- Missing construction control plan
- Insufficient structural information
- Golden thread deficiencies
Read your notice carefully - the BSR must give specific reasons.
-
Decide your next steps
You have two options: challenge the decision (review, then appeal) or resubmit.
When to challenge
- The BSR misinterpreted your application or regulations
- You have evidence that was not properly considered
- The rejection reasons are factually incorrect
Review request deadline: 21 days from the decision.
When to resubmit
- The rejection identifies genuine gaps
- You can address the deficiencies
- Appealing would take longer than fixing the issues
-
If you choose to challenge the decision
You must first request a review by the BSR within 21 days of the decision (Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, regulation 48). If you disagree with the review outcome, you can then appeal to the First-tier Tribunal within 21 days of the review decision (regulation 49). Grounds include an error of fact, the decision being wrong in law, unreasonableness, or procedural failure.
gov.uk
Building control approval for higher-risk buildings (opens in a new tab)
BSR guidance on the approval process, including reviews and appeals
-
Strengthen your resubmission
Address every issue the BSR identified. Common areas to strengthen:
- Fire safety strategy: Engage a competent fire engineer
- Competence evidence: CVs, qualifications, BSI Flex 8670 references
- Construction control plan: Include change control procedures
- Golden thread plan: Digital information management approach
Prepare for Gateway 2
Gateway 2 requirements and what to include
-
Timeline considerations
- Review and professional advice: 1-2 weeks
- Additional technical work: 2-6 weeks
- Prepare revised application: 1-2 weeks
- BSR assessment: 12 weeks statutory period for new buildings (8 weeks for work to an existing higher-risk building) - since the 2025 fast-track reforms most new applications are determined within or close to this
Total delay: Often 4-6 months including rework time - check the BSR's latest published determination data and factor this into stakeholder communications.