CDM compliance quick check

Quick CDM checklist before construction begins. Four key actions: check if notifiable, appoint duty holders, submit F10 if required, ensure construction phase plan exists.

Construction & Property Running a Business Updated 15 September 2026
4 milestones references 5 guides

CDM pre-construction checklist

Four compliance checks before construction starts. Run through in order.

  1. Is your project notifiable?

    Quick check:

    • Will construction last longer than 30 working days AND have more than 20 workers (21 or more) on site simultaneously at any point? Notifiable
    • Will total person-days exceed 500? Notifiable
    • Neither threshold met? Not notifiable (but CDM still applies)
  2. Appoint Principal Designer and Principal Contractor

    Required if: More than one contractor will work on the project (simultaneously or sequentially).

    England building work: these CDM appointments are separate from the Building Regulations principal designer and principal contractor appointments (Building Regulations 2010 Part 2A, SI 2023/911), which are also required for building work in England subject to building regulations with more than one contractor. Make both sets of appointments.

    Appoint Principal Designer

    Must be a designer with control over pre-construction phase. Appoint in writing before design work starts.

    Appoint Principal Contractor

    Must be a contractor. Appoint in writing before construction phase begins.

  3. Submit F10 notification (if notifiable)

    If your project exceeds notification thresholds, notify HSE before construction begins.

    Submit F10 notification to HSE

    Online form takes 10-15 minutes. You need project details, duty holder contact info, and planned dates.

    hse.gov.uk

    HSE F10 online form (opens in a new tab)

    Submit notification directly via HSE website

  4. Ensure construction phase plan exists

    Mandatory for ALL projects - not just notifiable ones. No plan = no construction.

    Create construction phase plan

    Principal Contractor prepares this before construction starts. Must address specific project risks.

    Pre-construction deadlines

    ActionDeadline
    Appoint Principal DesignerBefore design work starts (ideally) / Before construction (latest)
    Appoint Principal ContractorBefore construction phase begins
    Submit F10 (if notifiable)Before construction phase begins
    Construction phase plan readyBefore any construction work starts
    Welfare facilities in placeBefore workers arrive on site

    CDM client duties - full guide

    Comprehensive guide to all your CDM obligations as a construction client