Work out which role you hold
A contractor is any person, including a non-domestic client, who in the course or furtherance of a business carries out, manages or controls construction work. HSE guidance says contractors include subcontractors, sole traders and self-employed individuals.
A principal contractor is the contractor the client appoints to perform the duties in regulations 12 to 14 of the Construction (Design and Management) Regulations 2015 (CDM 2015). A client appoints one where more than one contractor works on the project, or it is reasonably foreseeable that more than one will work on it at any time. A sole contractor is the only contractor on the project, and is never a principal contractor.
What each role carries
| Role | Duties |
|---|---|
| Contractor | Planning, managing and monitoring your own work, your workers' skills, supervision and information, site access, welfare and competence |
| Principal contractor | The contractor duties that apply to it, plus the regulation 12 to 14 duties: planning, managing, monitoring and coordinating the whole construction phase, drawing up the construction phase plan, site induction, access, welfare, liaison with the principal designer and worker consultation |
| Sole contractor | The contractor duties that apply to it, plus taking account of the general principles of prevention and drawing up the construction phase plan |
Check before you start work
HSE says contractor duties apply as soon as you are appointed to the project to carry out construction work.
-
Check the client knows their duties
You must not carry out construction work unless you are satisfied that the client is aware of the duties the client owes under CDM 2015. On a sole-contractor job, HSE advises you to liaise directly with the client to establish this, for example at early meetings.
-
Make sure reasonable steps have been taken to stop unauthorised access
You must not begin work on a construction site unless reasonable steps have been taken to prevent access by unauthorised persons. On a small and straightforward job with more than one contractor, HSE says a phone call or early meeting with the principal contractor before you start work on site can be enough. On a sole-contractor job, HSE says to do whatever is proportionate.
-
Check each person you take on has, or is in the process of obtaining, the skills
You must not employ or appoint a person to work on a construction site unless that person has, or is in the process of obtaining, the skills, knowledge, training and experience to carry out the tasks allocated to them in a manner that secures the health and safety of any person working on the site.
Have the competence for your role and take reasonable steps to satisfy yourself about those you appoint
If you are appointed to work on a project, you must have the skills, knowledge and experience, and if you are an organisation the organisational capability, to fulfil the role in a manner that secures the health and safety of any person affected by the project. You must not accept an appointment unless you do.
If you are responsible for appointing a designer or another contractor, such as a subcontractor, you must take reasonable steps to satisfy yourself that they meet the same conditions.
HSE says the level should be proportionate to the complexity of the work and the range and nature of the risks. It gives training and continuing professional development records, membership of professional bodies and references from previous construction work as examples of evidence of skills, knowledge and experience. For organisational capability, its examples are a pre-qualification assessment by a member of the Safety Schemes in Procurement Forum, or a self-assessment against the standard questions in Build UK's Common Assessment Standard. It also says sole reliance should not be placed on industry certification cards.
Plan, manage and monitor your own work
You must plan, manage and monitor construction work carried out by you or by workers under your control, so that, so far as is reasonably practicable, it is carried out without risks to health and safety.
Where there is more than one contractor working on the project, you must also comply with any directions given by the principal designer or the principal contractor, and with the parts of the construction phase plan that are relevant to your work. Neither duty applies where you are the only contractor.
Give your workers supervision, instructions and information
You must provide each worker under your control with appropriate supervision, instructions and information so that construction work can be carried out, so far as is reasonably practicable, without risks to health and safety. The information must include:
- a suitable site induction, where the principal contractor has not already provided one
- the procedures to be followed in the event of serious and imminent danger to health and safety
- information on risks to health and safety identified by the risk assessment under regulation 3 of the Management of Health and Safety at Work Regulations 1999, or arising out of another contractor's undertaking and of which you, as the contractor in control of the worker, ought reasonably to be aware
- any other information the worker needs to comply with the relevant statutory provisions
Anyone who is required by CDM 2015 to provide information or instruction must make sure it is comprehensible and provided as soon as practicable.
Cooperate and report danger
You must cooperate with any other person working on or in relation to the project, at the same or an adjoining construction site, to the extent necessary to enable any person with a duty or function to fulfil that duty or function under CDM 2015.
If you work on the project under the control of another person, you must report to them anything you are aware of in relation to the project which is likely to endanger your own health or safety or that of others.
If you are the principal contractor
Plan, manage, monitor and coordinate the construction phase
You must plan, manage and monitor the construction phase and coordinate matters relating to health and safety during it, so that, so far as is reasonably practicable, construction work is carried out without risks to health or safety.
When deciding the design, technical and organisational aspects of planning work that takes place at the same time or in succession, and when estimating how long the work or work stages will take, you must take into account the general principles of prevention.
HSE says the effort should be proportionate to the size and complexity of the project and the risks involved, and that you do not have to undertake detailed supervision of contractors' work.
Organise cooperation and coordinate the contractors
You must:
- organise cooperation between contractors, including successive contractors on the same construction site
- coordinate implementation by the contractors of applicable legal requirements for health and safety
- ensure that employers and, if necessary for the protection of workers, self-employed persons apply the general principles of prevention in a consistent manner and, where required, follow the construction phase plan
Induction and site access
You must ensure that a suitable site induction is provided, and that the necessary steps are taken to prevent access by unauthorised persons to the construction site. HSE says an induction should be site specific and highlight any particular risks, that occasional and one-off visitors also need an induction proportionate to the visit, and that escorted visitors need only the main hazards and controls.
The construction phase plan
During the pre-construction phase, and before setting up a construction site, you must draw up a construction phase plan, or make arrangements for one to be drawn up. The plan must set out the health and safety arrangements and site rules and, where applicable, include specific measures for work in the categories in Schedule 3.
Throughout the project you must ensure that the plan is appropriately reviewed, updated and revised from time to time, so that it continues to be sufficient to ensure that construction work is carried out, so far as is reasonably practicable, without risks to health or safety.
Liaison with the principal designer
You must liaise with the principal designer for the duration of the principal designer's appointment. Share information relevant to the planning, management and monitoring of the pre-construction phase and the coordination of health and safety matters during that phase. During the project you must also give the principal designer any information in your possession that is relevant to the health and safety file.
Consulting and engaging workers
You must make and maintain arrangements that enable you and the workers engaged in construction work to cooperate effectively in developing, promoting and checking the effectiveness of measures for the workers' health, safety and welfare.
You must consult those workers or their representatives in good time on matters connected with the project that may affect their health, safety or welfare, in so far as they or their representatives have not been similarly consulted by their employer. Where consultation has already taken place through a direct employer, HSE says it is not required again. HSE says the duty is in addition to every employer's own duty to consult its employees under separate legislation.
You must also ensure that those workers or their representatives can inspect and take copies of any information you have, or that CDM 2015 requires to be provided to you, relating to the health, safety or welfare of workers at the site. That does not extend to information:
- whose disclosure would be against the interests of national security
- that you could not disclose without contravening a prohibition imposed by or under an enactment
- relating specifically to an individual, unless that individual has consented to its disclosure
- whose disclosure would, for reasons other than its effect on health, safety or welfare at work, cause substantial injury to your undertaking or, where another person supplied it, to that person's undertaking
- obtained for the purpose of bringing, prosecuting or defending legal proceedings
If you are the only contractor
You must take account of the same general principles of prevention when deciding the design, technical and organisational aspects of planning work and when estimating how long it will take.
You must also draw up a construction phase plan, or make arrangements for one to be drawn up, as soon as is practicable before setting up a construction site. The plan must meet the same content requirements as a principal contractor's plan. HSE says it should be proportionate to the size and scale of the job, and that a simple plan before work starts is usually enough for a small job.
Take on the client's duties for a domestic client
A domestic client is a client for whom the project is not carried out in the course or furtherance of a business of that client. HSE guidance says that means work on the client's own home or a family member's home. HSE also says that landlords, housing associations, local authorities, charities and other businesses that own domestic property are not domestic clients, and neither is a client having work done in connection with a business attached to domestic premises, such as a shop.
For a domestic client, the client duties in regulations 4(1) to (7) and 6 must be carried out by:
- the contractor, for a project where there is only one contractor
- the principal contractor, for a project where there is more than one contractor
- the principal designer, where there is a written agreement that the principal designer will fulfil those duties
Those duties include making suitable arrangements for managing the project, providing pre-construction information, ensuring a construction phase plan is drawn up and notifying a notifiable project. You carry them in addition to your own duties. The duties in regulation 8(3), (4) and (6) (taking reasonable steps to check the competence of those you appoint, cooperating, and giving comprehensible information) also pass to the same person, to the extent that they are applicable to a domestic client.
If a domestic client fails to appoint a principal contractor on a project with more than one contractor, the contractor in control of the construction phase is the principal contractor. Regulation 5(3) and (4), under which a client who fails to appoint a principal designer or principal contractor carries out their duties itself, do not apply to a domestic client.
HSE says that on a single-contractor project, compliance with your own contractor duties is taken as compliance with the relevant client duties, to the extent necessary given the risks. HSE also says that where a written agreement passes the client duties to the principal designer, the principal contractor works to the principal designer as the client.
Welfare facilities
If you are the principal contractor, you must ensure that facilities complying with Schedule 2 are provided throughout the construction phase. HSE says they must be available before any construction work starts and should be maintained until the end of the project.
Every contractor must ensure, so far as is reasonably practicable, that the requirements of Schedule 2 are complied with so far as they affect the contractor or any worker under that contractor's control. HSE says this extends only to your own employees and anyone else working under your control, and that on a project with more than one contractor you should discuss and agree the arrangements with the principal contractor, who has a similar duty.
Schedule 2 sets these minimum facilities.
Sanitary conveniences
- Provide suitable and sufficient sanitary conveniences, or make them available, at readily accessible places.
- So far as is reasonably practicable, rooms containing them must be adequately ventilated and lit, and the conveniences and rooms kept clean and orderly.
- Provide separate rooms for men and women, except where and so far as each convenience is in a separate room whose door can be secured from the inside.
Washing facilities
- So far as is reasonably practicable, provide or make available suitable and sufficient washing facilities at readily accessible places, including showers if the nature of the work or health reasons require them.
- Provide them in the immediate vicinity of every sanitary convenience and in the vicinity of any changing rooms required, whether or not also provided elsewhere.
- They must include a supply of clean hot and cold, or warm, water, which must be running water so far as is reasonably practicable, with soap or other suitable means of cleaning and towels or other suitable means of drying.
- Rooms containing them must be sufficiently ventilated and lit, and the facilities and rooms kept clean and orderly.
- Provide separate facilities for men and women, except where they are in a room whose door can be secured from the inside and the facilities in each room are intended for one person at a time. That rule does not apply to facilities for washing hands, forearms and the face only.
Drinking water
- Provide or make available an adequate supply of wholesome drinking water at readily accessible and suitable places.
- Where necessary for reasons of health or safety, conspicuously mark every supply with an appropriate sign.
- Where you provide a supply of drinking water, also provide a sufficient number of suitable cups or other drinking vessels, unless the supply is a jet from which people can drink easily.
Changing rooms and lockers
- Provide or make available suitable and sufficient changing rooms at readily accessible places if a worker has to wear special clothing for construction work and cannot, for reasons of health or propriety, be expected to change elsewhere.
- Where necessary for reasons of propriety, provide separate changing rooms for, or separate use of rooms by, men and women.
- Changing rooms must have seating and, where necessary, facilities to dry special clothing and personal clothing or effects.
- Where necessary, provide or make available at readily accessible places suitable and sufficient facilities for locking away special clothing not taken home, workers' own clothing not worn during working hours, and personal effects.
Rest rooms and rest areas
- Provide or make available suitable and sufficient rest rooms or rest areas at readily accessible places.
- They must have adequate tables and adequate seating with backs for the number of people likely to use them at any one time.
- Where necessary, they must include suitable facilities for a pregnant or nursing worker to rest lying down.
- They must include suitable arrangements for preparing and eating meals, and the means for boiling water.
- They must be maintained at an appropriate temperature.
Know when a project is notifiable
A working day is any day on which construction work takes place. HSE says every day on which construction work is likely to be carried out counts, including weekends and holidays, even if the work that day is short. It also says the client may ask the principal contractor or a contractor to submit the notice or to display it, and that the CDM 2015 duties apply whether or not the project is notifiable.
Penalties
Legal basis
Primary legislation and key regulations
Official guidance
Construction phase plan for a busy builder, CIS80 (HSE) (opens in a new tab)
HSE · Great Britain
Managing health and safety in construction (opens in a new tab)
Code of Practice · HSE · Great Britain
Principal contractors: roles and responsibilities (opens in a new tab)
HSE · Great Britain
Domestic clients: roles and responsibilities (opens in a new tab)
HSE · Great Britain
Contractors: roles and responsibilities (opens in a new tab)
HSE · Great Britain
Are you a principal contractor? (opens in a new tab)
HSE · Great Britain
Are you a contractor? (opens in a new tab)
HSE · Great Britain