Demolition safety and compliance
How to comply with demolition safety requirements in England and Wales. Covers Section 80/81 demolition notices, asbestos refurbishment …
How to manage temporary works safely on construction projects. Covers the temporary works coordinator role, BS 5975 procedures, design checking, permit to load and strike, and handover requirements for formwork, propping, falsework, and shoring.
If your construction project uses temporary structures like formwork or propping, you must follow a formal process to manage them safely. Appoint a Temporary Works Coordinator, follow BS 5975 procedures, and make sure designs are checked. Failure to do so is a criminal offence and can cause serious injuries.
How to comply with demolition safety requirements in England and Wales. Covers Section 80/81 demolition notices, asbestos refurbishment …
Pre-start checklist for structural works covering demolition notices, asbestos surveys, temporary works design, excavation permits, LOLER examinations, and …
HSE requirements for safe excavation and foundation work on construction sites. Covers trench support systems, edge protection, safe …
LOLER 1998 requirements for crane and lifting operations on construction sites. Covers appointed persons, lift planning, thorough examination …
How to comply with the Construction (Design and Management) Regulations 2015 (CDM 2015). Covers duty holder responsibilities, when …
If your construction project involves formwork, falsework, propping, shoring, cofferdams, or any other temporary structure that supports permanent works during construction, you must manage those temporary works through a formal process. Failing to ensure temporary works are properly designed, checked and controlled breaches the Construction (Design and Management) Regulations 2015 (in particular regulation 19, stability of structures) and is a criminal offence.
Temporary works failures cause deaths and serious injuries on UK construction sites. Collapses of falsework, formwork, and propping systems happen when temporary works are not properly designed, checked, erected, or removed. HSE investigates every serious incident and prosecutes where duties have been breached.
This guide explains the procedures you must follow to manage temporary works safely, including appointing a Temporary Works Coordinator, following BS 5975, and operating permit-to-load and permit-to-strike systems.
You need a formal temporary works management process whenever your project involves any of the following:
Even simple propping during wall removal in a refurbishment project requires formal temporary works management. The scale of the process should be proportionate to the risk, but the core steps always apply.
The principal contractor should appoint a Temporary Works Coordinator (TWC) for every project that involves temporary works, in line with BS 5975. The TWC is an industry-practice role, not a statutory appointment - the legal duties are the general CDM 2015 ones (regulation 13 management duties and regulation 19 stability of structures) - but HSE expects a systematic approach equivalent to BS 5975, and appointing a TWC is how those duties are normally discharged. The appointment should be made in writing and recorded in the construction phase plan.
The TWC is the single point of responsibility for all temporary works on the project. Their duties include:
On smaller projects, the site manager or project manager may act as TWC provided they have the required competence. On larger or more complex projects, the TWC should be a dedicated role held by a chartered or incorporated engineer with temporary works experience.
BS 5975 sets out the standard process for managing temporary works. The standard was reissued in December 2024 as two parts: BS 5975-1:2024 (management and procedures) and BS 5975-2:2024 (falsework design), replacing the previous BS 5975:2019 edition. Although BS 5975 is not itself legislation, following it demonstrates compliance with CDM 2015 duties. HSE expects contractors to follow BS 5975 or an equivalent systematic approach.
The BS 5975 process follows a structured sequence that must not be shortcut:
The TWC must maintain a temporary works register listing every item of temporary works on the project. For each entry, the register should record:
The register is a live document that must be updated as temporary works progress through the project. It forms part of the project health and safety records and should be available for HSE inspection at any time.
Temporary works involving particular risks under CDM 2015 Schedule 3 require specific risk control measures in the construction phase plan. Work near unstable structures, heavy prefabricated elements, and operations with risk of burial are all Schedule 3 categories that commonly overlap with temporary works. The TWC should coordinate with the principal contractor to ensure these measures are documented and communicated to all relevant personnel.
When temporary works support a structure during alteration or partial demolition, the structural stability requirements are especially important. The TWC must work closely with the structural engineer to ensure the temporary support scheme accounts for the actual load path through the building at every stage of the works, not just the final condition.
Handover of temporary works between trades or contractors is a high-risk point. Many temporary works failures occur when one contractor erects temporary support and another contractor later modifies or removes it without understanding the design intent.
To manage handover safely:
Before starting any work involving temporary works:
If you are unsure whether your project requires formal temporary works management, it almost certainly does. Any work involving structural support during construction falls within the scope of BS 5975. Seek advice from a chartered engineer with temporary works experience if needed.